1. What is the Rebuild by Design – Hudson River Project?
The Rebuild by Design (RBD) project is a flood resiliency initiative launched by the United States Department of Housing and Urban Development (HUD) to improve resilience in regions affected by Superstorm Sandy. The New Jersey Department of Environmental Protection (NJDEP) was awarded nearly $300 million by HUD to lead the Rebuild by Design - Hudson River (RBDH) project, which aims to protect Hoboken and portions of Jersey City and Weehawken against future flooding caused by storm surge.
2. What are the main components of the Rebuild by Design – Hudson River Project?
The RBDH project aims to mitigate flooding impacts using four approaches:
The RBDH project is funding the implementation of this approach through three key infrastructure projects:
The City of Hoboken’s investments to mitigate stormwater flooding from heavy rain events using resiliency parks, such as ResilienCity Park, as well as green infrastructure projects, will work in tandem with RBDH’s investments to address storm surge flooding from the Hudson River.
3. Why is the Rebuild by Design-Hudson River Project necessary?
During Superstorm Sandy in October of 2012, 80% of the City of Hoboken was flooded with an estimated 500 million gallons of coastal storm surge and many areas of Hoboken were without power for weeks. The National Guard was deployed to help evacuate residents from their homes where they were stranded. It is estimated that more than $100 million in private property damage and $10 million in public property damage occurred. The Rebuild by Design – Hudson River project aims to mitigate storm surge flooding, limit storm surge damage, remove 80% of the city from the flood plain, and reduce flood insurance costs for residents.
1. What is the Rebuild by Design – Hudson River Project?
The Rebuild by Design (RBD) project is a flood resiliency initiative launched by the United States Department of Housing and Urban Development (HUD) to improve resilience in regions affected by Superstorm Sandy. The New Jersey Department of Environmental Protection (NJDEP) was awarded nearly $300 million by HUD to lead the Rebuild by Design - Hudson River (RBDH) project, which aims to protect Hoboken and portions of Jersey City and Weehawken against future flooding caused by storm surge.
2. What are the main components of the Rebuild by Design – Hudson River Project?
The RBDH project aims to mitigate flooding impacts using four approaches:
The RBDH project is funding the implementation of this approach through three key infrastructure projects:
The City of Hoboken’s investments to mitigate stormwater flooding from heavy rain events using resiliency parks, such as ResilienCity Park, as well as green infrastructure projects, will work in tandem with RBDH’s investments to address storm surge flooding from the Hudson River.
3. Why is the Rebuild by Design-Hudson River Project necessary?
During Superstorm Sandy in October of 2012, 80% of the City of Hoboken was flooded with an estimated 500 million gallons of coastal storm surge and many areas of Hoboken were without power for weeks. The National Guard was deployed to help evacuate residents from their homes where they were stranded. It is estimated that more than $100 million in private property damage and $10 million in public property damage occurred. The Rebuild by Design – Hudson River project aims to mitigate storm surge flooding, limit storm surge damage, remove 80% of the city from the flood plain, and reduce flood insurance costs for residents.
The New Jersey Department of Environmental Protection (NJDEP) will begin the next phase of the Rebuild by Design – Hudson River project, which includes major construction on 15th Street to install underground infrastructure for a sliding flood gate designed to protect Hoboken from storm surge flooding.
Activities include:
Starting July 7, the following streets will be closed to vehicular through-traffic 24/7 for approximately four months:
Traffic mitigation measures include:
5. Will I be able to access my garage?
Yes. the parking garages at 1499 Park Ave. and LAZ Parking will be maintained.
Yes. The following pedestrian routes will remain open:
Yes. Temporary curb adjustments will include:
Yes. Emergency access will be maintained via 14th and Garden Streets, in coordination with the Hoboken Fire Department.
This phase is expected to take approximately 4 months using multiple crews and extended hours. Harborside Park, where the sliding floodgate will be housed during sunny days, is expected to be completed in 2027.
1. What progress has been made so far on the Rebuild by Design project?
The Sewer Separation Modification (SSM) contract was completed in July 2022, separating portions of the sewer system to prevent water from surcharging under the Resist structure.
In October 2023, construction began on a new Harborside Park, which will integrate flood walls and gates to mitigate storm surge flooding while providing open space amenities for the community.
2. What will be in Harborside Park when it is completed?
Once completed, the new Harborside Park will serve as both a critical flood protection asset and a vibrant community space for Hoboken residents. Located at 15th Street and Park Avenue, this nearly 3-acre park will include several amenities designed to enhance quality of life while providing robust flood defenses.
Key features of Harborside Park will include:
Harborside Park will be the first in New Jersey to combine elevated flood protection features with community amenities, setting a new standard for resilient urban park design.
1. Where can I learn more about the Rebuild by Design-Hudson River project?
The NJDEP has a webpage dedicated to the Rebuild by Design – Hudson River project, which includes past meeting materials and presentations and more. Go to https://dep.nj.gov/floodresilience/rebuild-by-design-hudson-river/.
2. How can I stay updated on the latest construction schedules?
Weekly construction schedules are available online at www.hobokennj.gov/construction.
3. How can I provide feedback or ask questions?
Your feedback is valuable as the project team continues to work on improving traffic management and responsiveness to any issues.
If you have further questions, concerns, or if you would like to learn more about the project, please contact the NJDEP Community Construction Liaison for the Rebuild by Design project Isabella Brascetta at 1-800-252-0219 or rbdhinquiries@portal3.pbid.com.