Construction Updates

Check back here for weekly updates to ongoing construction and quality of life projects in the City of Hoboken.

Be advised, schedules are subject to change depending on weather, construction logistics, or other circumstances.

For daily road closures, follow the Hoboken Office of Emergency Management on X: @HobokenOEM.

Rebuild by Design Hudson River Project/Jersey Ave. Closure

The New Jersey Department of Environmental Protection (NJDEP) is continuing the construction phase for the Rebuild By Design Hudson River Project – Resist Alignment Coastal Defense Contract. The Resist structure is a floodwall and levee system aimed to protect the Project Area from coastal flooding threats associated with storm surge.

To facilitate construction, beginning July 7, 15th Street will be closed from Park Avenue to Bloomfield Street as well as Garden Street between 15th Street and 14th Street and the alleyway between Garden Street and Bloomfield Street will be closed to vehicular through-traffic 24/7 for approximately four months. Please see below for more information on the 15th Street closure and traffic mitigation efforts.

The following preliminary fieldwork is anticipated to take place in the Resist – North Work Area and the Resist South Work Area during the week of June 30 to July 5 between the hours of 8 a.m. and 6 p.m.

(No work scheduled for Friday 07/04/25 in observance of the Independence Day Holiday.)

RESIST – SOUTH:

Washington St (Hoboken)

  • Sidewalk Restoration

New Jersey Transit Yard (Hoboken)

  • Topping Slab

Jersey Ave (Jersey City)

  • Install Bike Lane Detour – This Will Be Off of the Roadway, to the West of Jersey Ave

Private Property (Jersey City)  

  • Excavate / Install Sheets
  • Mud Slab, Forms and Concrete

RESIST – NORTH:

Bloomfield Alley between Bloomfield and Washington (Hoboken)

  • Forms and Concrete Pour

Harborside Park (Hoboken)

  • Retaining Walls Forms and Concrete  

15th Street Closure starting on July 7

Starting on July 7, the New Jersey Department of Environmental Protection will continue construction on the resist feature of the Rebuild by Design - Hudson River project, which will protect Hoboken from storm surge flooding.  This phase of the project aims to install underground infrastructure for a sliding flood gate to help prevent storm surge flooding from the Hudson River. During Hurricane Sandy, this type of flooding inundated the City with over 500 million gallons of water causing more than $100 million in private property damage.  

The construction will include excavation activities for the resist structure, pouring and curing of the monolithic foundational slab for the gate, PSE&G utility relocation work, installation of gate rails, new concrete curb and sidewalk installation, gate installation, form and rebar work, as well as roadway paving and restriping among other construction activities.  

To facilitate construction, 15th Street from Park Avenue to Bloomfield Street as well as Garden Street between 15th Street and 14th Street and the alleyway between Garden Street and Bloomfield Street will be closed to vehicular through-traffic 24/7 for approximately four months. Parking garage access for 1499 Park Ave. and LAZ Parking Garages will be maintained.

To help vehicular circulation, traffic mitigation plans include:

  • Traffic signal timing changes at 11 area intersections:  
  • Up to three Portable Variable Message Signs  
  • Up to five Police Officers directing traffic at key intersections as needed  
  • Installation of new Miovision cameras at certain intersections to monitor and manage circulation

Read more here: https://local.nixle.com/alert/11694037/

For more information about this project, see the City’s FAQ page here:  https://www.hobokennj.gov/resources/rebuild-by-design-hudson-river-project-faq.

Project Background

The Rebuild by Design - Hudson River Project is a comprehensive urban stormwater management program that takes a multi-faceted approach intended to address flooding from both major storm surge and high tide as well as from heavy rainfall events. These events often occur individually, but can also occur together, increasing their impacts. The program includes four components: Resist, Delay, Store and Discharge.  

The NJDEP is implementing the Resist component of the project concept, while the City of Hoboken has and continues to lead efforts implementing the Delay, Store and Discharge components. This portion of construction is Phase II of the Resist component. Phase I included implementation of Sewer System Modifications (SSM) and was completed in July 2022. Phase II will include the construction of the Resist Alignment, a floodwall and levee system aimed to protect the Project Area from coastal flooding threats associated with storm surge. Construction for Phase II is beginning with the current test pitting work being described above.  

This United States Department of Housing and Urban Development is funding the project, allocating $230 million to the overall Rebuild by Design Hudson River Project. Additional funding has been allocated to this project through the FEMA Building Resilient Infrastructure and Communities grant program and through an American Rescue Plan Covid State Fiscal Recovery Funding allocation.

QUESTIONS?  If you have questions, or would like to learn more about the project, please contact your Community Construction Liaison Isabella Brascetta | 1-800-252-0219 | rbdhinquiries@portal3.pbid.com

No items found.
Waterfront Reconstruction Project

The Waterfront Reconstruction Project (formerly known as the Sinatra Drive Seawall Rehabilitation Project) will replace the aging and eroding concrete seawall beneath portions of Sinatra Drive and the Hoboken waterfront walkway. The project focuses on stabilizing and replacing the seawall and walkway along the eastern portion of Sinatra Drive, from the gazebo near Seventh Street to the skate park near Ninth Street, where erosion is most severe. This initiative is part of a larger effort to ensure the safety and longevity of the waterfront infrastructure.  

Mobilization activities will begin on April 7, 2025 and on or about, April 10, 2025, a new traffic pattern will be put into place to allow for construction which will include the closure of the eastern lane of Sinatra Drive from approximately Fifth Street north to approximately Sinatra Drive North. This closure will be in effect 24/7. No southbound traffic will be permitted. Southbound drivers must instead use Hudson Street. The western lane of Sinatra Drive will be open to northbound vehicles. In addition, the sidewalk on Sinatra Drive in the construction area, will be closed to pedestrians 24/7 in the construction area.  

Construction and closures are anticipated to last through fall of 2025.

More on the Waterfront Reconstruction Project can be found here: https://local.nixle.com/alert/11502705/?sub_id=0

The following work and traffic management activities are anticipated for Monday, June 30 through Saturday, July 2, between the hours of 8 a.m. and 8 p.m.:

Work Activities:

Frank Sinatra Drive between 7th and 9th Street

  • Excavation of trench to clear line for proposed steel combination wall
  • Selective demolition
  • Installation of pipe piles for steel combi-wall

Traffic Impacts:

  • No southbound vehicular or bicycle traffic is allowed on Sinatra Drive from Sinatra Drive North through Fifth Street.
  • Southbound traffic will detour to Hudson and/or Washington Street.
  • Oversized trucks will detour to Washington Street.
  • Northbound lanes will remain open to vehicular traffic, bicycles, and emergency vehicles.  
  • The sidewalk will be closed to pedestrians on both sides of Sinatra Drive between Fifth Street and Sinatra Drive North.
  • Sinatra Drive will be FULLY closed in both directions overnight, between the hours of 12 a.m. and 6 a.m., until further notice.  

*Sinatra Drive will be fully closed to vehicular traffic on Sundays between 8 a.m. and 12 p.m. for Sinatra Streets every weekend until further notice. MORE: https://www.hobokennj.gov/resources/summer-streets

Traffic Management:

  • Hoboken Police will be on site from 6 a.m. through 12 a.m.
  • Temporary No Parking signs will be posted in advance of any parking restrictions in the construction area.

No items found.
207-209 Jefferson Street Demolition

The City’s contractor, Adamo Brothers Construction, will be demolishing the two residential buildings located at the property of 207-209 Jefferson Street. The City acquired the properties in December 2023, and after demolition, the properties will be used for parking Hoboken Fire Department vehicles.  

The following work activities for the City Hall Portico restoration project are anticipated for the week of June 23, 2025, between the working hours of 8 a.m. and 4 p.m.:  

Work Activities:  

  • Backfill the excavated area  
  • Replace curb and sidewalk along Jefferson Street in front of the properties

Traffic and Pedestrian Impacts:  

  • A portion of the sidewalk on Jefferson Street between Second Street and Third Street adjacent to the project site will be temporarily restricted throughout the duration of demolition.  
  • Temporary No-Parking signs will be posted at parking spaces in front of the project site roadway at these locations throughout the duration of demolition.  
No items found.
Church Square Park Improvements - Phase 1

The City of Hoboken is moving forward with plans to improve and upgrade Church Square Park. The upgrades will include a new inclusive toddler playground in the southwest portion of the park, a new open lawn area in place of the old toddler playground, a landscaped buffer along the existing dog run, and the addition of new public restrooms. The improvements will be consistent with the park's historic character and were identified by the public during preparation of the Church Square Park Vision Plan.

For more information on the Church Square Park Vision Plan and Improvement Project see here: https://www.hobokennj.gov/resources/church-square-park-vision-plan\

The following work and traffic management activities are anticipated for the week of June 30, 2025, during the hours of 8 a.m. to 4 p.m.:  

Work Activities:  

  • Utility Building/Restroom Footings
  • Play Equipment Footings
  • Bench Footings and installation

Traffic Management Activities:  

  • Temporary Parking Restrictions will be in place on 4th Street between Garden Street and Willow Avenue.

Pedestrian Access Restrictions:

  • The Park Entrance at Garden Street and 4th Street will be closed until early July.
  • The Park Entrance at Willow Avenue and 4th Street will be closed until early July.
  • Temporary Sidewalk closures will be in effect at times.  
  • Signage will be posted.

No items found.
Hudson Place Water Main Improvements

The Hudson Place Area Water Main Improvement project involves the replacement of 850 feet of existing water mains. This is part of the City’s Water System Renewal Program, to modernize Hoboken’s drinking water infrastructure and reduce the need for emergency repairs. By the end of 2025, it is anticipated that 28,700 feet of aged water mains will have been replaced.  

Beginning on Monday, May 19, the City’s contractor will replace outdated 8-inch and 6-inch water mains with new, larger 12-inch water mains, install new service lines to the curb, and replace the hydrants along Hudson Place between River Street and Warrington Plaza, on Sinatra Drive between Newark Street and First Street, and replace water services on River Street between Hudson Place and Newark Street.  

The Hudson Place Water Main Improvement project is anticipated to be complete by July 2, 2025, although the schedule is subject to change.  

Read more about this project here: https://local.nixle.com/alert/11595083/

The following construction activities and traffic management are anticipated to take place from Monday June 30, 2025, through Friday, July 4, 2025, between the hours of 6 a.m. to 6 p.m.:  

Construction Activities:

  • Service and hydrant transfers

Traffic Impacts/Management

  • 7/2: No parking on both sides of Hudson Place from River Street to dead end.
  • 7/2: Hudson Place from River Street to dead end closed to vehicular traffic.
  • Access will be maintained to the parking lot for NJTPD personnel.
  • Due to excavations in the north sidewalk of Hudson Place, pedestrian traffic will be detoured around work zones.

The temporary taxi stand  on Newark Street has been relocated to the southwestern curb of Hudson Place, between Hudson Street and River Street.

No items found.
Hudson County Park Avenue & Willow Avenue Bridge Repairs

Hudson County is repairing and restoring multiple bridges across the county including in Hoboken, Weehawken, and Jersey City. The rehabilitation efforts aim to help maintain a steady flow of traffic and protect the traveling public.

The current work on Park Avenue and Willow Avenue in Hoboken & Weehawken which began in late March, is expected to continue through the end of July. The current work will repairs and restore the concrete substructure of the bridges, as well as repair and patch the bridge decks to protect cars and pedestrians from potholes or other potential vehicular risks.

The following construction activities will occur overnight on July 2 between the hours of 9:00 PM and 5:00 AM.

Work Activities:

Park Ave between 14th Street in Hoboken and 19th Street in Weehawken

  • Full bridge closure for sounding and inspection.

Traffic Management:

  • Full bridge closure from 8pm to 5 am
  • Traffic heading North to Weehawken will be detoured from Park Ave on 14th Street to Willow Ave to 19th Street back to Park Avenue.
  • Traffic heading South to Hoboken will be detoured from Park Ave and 19th to Willow Ave to 14th Street, back to Park Ave.

No items found.
Madison Street Area Infrastructure Improvements

The Madison Street Area Infrastructure Improvements project will help mitigate localized flooding from rain events. The project scope includes replacing existing inlets, sewers, and water lines as well as elevating roadways, curbs, and sidewalks within the area. These improvements will alleviate the primary concerns by conveying stormwater into the sewer system.  

Work on the Madison Street Area Infrastructure Improvements currently requires a 24/7 closure of Madison Street between 9th and 10th Streets, as well as parking restrictions. In addition, the intersection of 10th and Madison will be closed through approximately June 20. Area residents will be kept apprised of the work and impacts on their quality of life.

Read the most recent update on this project here: https://agency.nixle.com/pub/11643907/

The following work and traffic management activities are anticipated for Monday, June 30th through Friday, July 4th between the hours of 8 a.m. and 4 p.m.:

Work Activities:  

Madison Street between 9th and 10th Street.

  • Install Helical Piles, Manhole, Precast structures, Maintain Sewer Bypass.
  • Install 36” sewer and 16” water main.
  • Backfill for the 36” sewer and 16” water main.
  • Install MH-764.

Traffic Management:

  • Parking spaces will be available on the east side of Madison Street between 10th and 11th.
  • No-Parking on the west side of Madison Street between 10th and 11th .
  • Madison Street between 9th and 10th Street will be closed
  • HPD will be on-site to assist with traffic management during construction.
  • Garage access will be maintained for 915 and 901 Madison Street.

As part of the traffic management plan for the Madison Street Infrastructure Improvement project, Citi Bike will temporarily relocate the docking station at Madison Street & 10th Street to the northeast corner of Monroe Street & 10th Street. The docking station will stay at that location until the end of April. Temporary No Parking Signs will be posted on parts of the east side of Monroe Street during the relocation.  

The Citi Bike docking station relocation is required to maintain access to bike share during the Madison Street resiliency and utility construction project (NHSA Madison Areawide Infrastructure Improvement Project).  

No items found.
NHSA H6/H7 Phase II: Adams Street Force Main

Underground Utilities Corp. is installing new high level storm sewers and a force main within the northeast portion of the City of Hoboken. These sewers will be connected into the stormwater storage tank at the Northwest Resiliency Park and the force main will connect from the H6/H7 pump station to the NHSA’s existing outfall in 15th Street.

Anticipated Construction Activities and Traffic Management for the period of 6/30/2025 through 7/5/2025 are as follows:

Construction Activities

  • Working on louvers, pump rails, and platforms for electrical installation for the pumps at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets.
  • Installation of curbs and curb walls on Adams Street between 14th and 15th Street.  

Traffic Management

  • Adams Street between 13th and 15th Streets will be open to thru traffic.
  • HPD officers will be present at all intersections within work zones.
  • 24/7 no parking signs will be in place on both sides of Adams Street between 14th and 15th Streets.

No items found.
Complete Streets Phase Two

Your Way Construction will be resurfacing various roadways throughout the City of Hoboken.  This work will include Vision Zero and resiliency improvements, including the installation of new bike lanes, high visibility crosswalks, curb extensions, green infrastructure upgrades, and roadway restoration.

Phase 2 of the Water Improvement Upgrades (WIU) Project represents the final restoration of roadways that were recently improved with new water mains, and new water services. The project includes Vision Zero and resiliency improvements, including the installation of new bike lanes, high visibility crosswalks, curb extensions, green infrastructure upgrades, and roadway restoration. The work, which begins on June 9 and will be completed on a rolling basis, is expected to last seven months. It includes the milling and paving of approximately twelve (12) blocks and three (3) intersections within the City of Hoboken,

Blocks include:  

  • Madison Street between 4th Street and 6th Street
  • Grand Street between 3rd Street and 8th Street
  • Jefferson Street between Newark Street and 1st Street
  • 7th Street between Adams Street and Grand Street
  • Adams Street between 8th Street and 9th Street
  • 8th Street between Adams Street and Jefferson Street
  • 6th Street from Adams Street to Grand Street
  • 8th Street from Adams Street to Grand Street

Intersections include:  

  • 7th Street and Monroe Street intersection
  • 7th Street and Madison Street intersection
  • 5th Street and Monroe Street intersection

The project includes the installation of eighteen (18) intersection curb bump outs, installation of seven (7) manufactured treatment devices, and all of the associated striping and signage required for all of the areas of work described.

The following construction activities and traffic management are anticipated to take place from Monday, June 30, 2025, through Friday, July 4, 2025, between the hours of 7:00 a.m. and 5 p.m. by Your Way Construction.  

Construction Activities:

  • Monday (6/30) - Drainage improvements and concrete bump out installation will take place at the northwest corner of Grand Street and 3rd Street.
  • Tuesday (7/1) - Drainage improvements and concrete bump out installation will take place at the southwest corner of Grand Street and 4th Street.
  • Wednesday & Thursday (7/2 & 7/3) - Drainage improvements and concrete bump out installation will take place at the northwest corner of Grand Street and 7th Street.
  • There will be no work on Friday (7/4) for the July 4th holiday.

Traffic Management:

  • On Monday (6/30), Third Street will be closed from Grand Street to Adams Street during working hours.  
  • On Tuesday (7/1), Fourth Street will be closed from Grand Street to Adams Street during working hours.
  • On Wednesday and Thursday (7/2 & 7/3), Seventh Street will be closed from Grand Street to Adams Street during working hours.
  • One-lane of traffic will remain open on Grand Street at all times to allow traffic to flow.  
  • Temporary No-Parking signs will be posted in advance of restrictions going into place.
  • Sidewalks will be closed at these locations during construction activities.  Pedestrian detours will be posted.
  • Hoboken Police will be onsite to assist with road closures and pedestrian detours.

Picture

No items found.
NHSA H6/H7 CSO Long Term Control Plan Project, Phase 3

Underground Utilities Corporation will be installing new sewer lines, and curb inlets will be installed to alleviate drainage and potential flooding issues in Northwest Hoboken. The goal of this project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River.

The following traffic impacts are anticipated to take place between 8 a.m. and 6 p.m. the week of June 30, 2026, by Underground Utilities Corp.:  

Traffic Impacts/Management

15th Street between Jefferson Street and Grand Street

  • No parking 24/7
  • Signs will be placed on both sides of the street.
  • Roadway closed to eastbound traffic from 8 a.m. to 6 p.m.
  • Eastbound traffic detoured to Jefferson Street and 16th Street.
  • Academy Bus Services can access work area to enter/exit their parking lots.  
  • Buses must use Jefferson Street and 16th Street to exit all parking lots to proceed to Willow Street as 15th Street eastbound is closed to traffic.

13th Street between Jefferson and Madison

  • No parking 24/7 signs will be placed on both sides of the street.

Jefferson Street between 13th Street and 16th Street  

  • No parking 24/7 both sides of the street  

Adams Street between 15th Street and 16th Street  

  • No parking 24/7 both sides of the streets
  • Road closed during working hours of 8 a.m. to 6 p.m.

Madison and Jefferson Street between 14th and 15th Street  

  • No parking 24/7 both sides of the streets  
  • Academy Bus Service re-configured entrance/exit routing

Grand Street between 15th and 16th Street

  • No parking 24/7 on both sides of the street.  

16th Street between Jefferson Street and Adams Street  

  • Section of roadway is open to two way traffic (east and west)
  • No Parking 24/7 both sides of the street

16th Street between Adams Street and Grand Street

  • No Parking 24/7 both sides of the street

13th Street between Adams Street and Grand Street

  • Road to be closed 24/7
  • No parking 24/7 on both sides of 13th Street between Adams Street and Clinton Street
  • Signs will be posted.
  • Residents will be allowed access in from Grand St to 1300 Grant St garage. 1200 Grand St garage to be accessed via 12th Street.
  • Traffic detour: Grand St to 11 St to Adams Street

Construction Activities

16th Street and Jefferson Street Intersection

  • Excavation of trench for Gas line relocation
  • Installation of new sewer piping

Jefferson Street

  • Sidewalk and Curb restoration on Jefferson at 14th
  • Installation of catch basins along Jefferson Street between 15th Street and 16th Street

Adams Street between 15th Street and 16th Street

  • Installation of piles, pile caps, concrete cradles
  • Installation of 18" Storm pipe
  • Installation of manholes

Madison Street between 13th and 14th

  • Sidewalk and Curb restoration
  • Monitoring Well Installation

15th Street and Adams Street Intersection

  • Installation of new sewer piping

15th Street between Adams Street and Grand Street

  • Installation of new sewer piping
No items found.
Hudson County Intersection Improvement Project

Hudson County’s Intersection Improvement Project will install a new signal at the intersection of Hudson and 11th Streets.  

The following construction activities and traffic impact/management is anticipated between the hours of 8 a.m. and 4 p.m. for the week of June 30rd:

Construction Activities

  • Install one traffic signal foundation and reconstruct the handicap ramp.
  • Work will be occurring on the north side of Hudson Street.  

Traffic Management

  • Hoboken Police Officers be onsite during working hours to assist with pedestrian safety.  

No items found.
Southwest Resiliency Park Expansion

Plans to expand Southwest Resiliency Park are part of Hoboken’s Rebuild by Design (“RBD”) - Hudson River Project and the City’s comprehensive water management strategy to delay, store, and discharge stormwater during intense rain events, The project is funded through a $6.24 million dollar grant from the Federal Emergency Management Agency (FEMA). The expanded park will include above ground green infrastructure and an underwater detention system to withhold 328,000 gallons of stormwater caused by heavy precipitation.

The following traffic impacts and management, and work activities are anticipated the week of June 30: 

Observer Highway at Harrison Street

  • Temporary lane closures will be in effect to complete curb replacement on Observer Highway between Harrison Street and the Light Rail tracks as well as the corner of Harrison Street and Observer Highway.
  • Police Traffic Directors will be in place and pedestrian MPT signage posted.

No items found.
Former Union Dry Dock Site Construction

In accordance with the lease between the City of Hoboken and NY Waterway for its temporary operations at the former Union Dry Dock site (901 Sinatra Dr.), NY Waterway will begin constructing approved site alterations within their leasehold area of the site. The initial construction work as part of the project will involve electrical improvements.  

In accordance with the license agreement between the City of Hoboken and NJDEP, NJDEP and its contractor, EE Cruz, for the RBD-HR project will be using a portion of the former Union Dock Site (901 Sinatra Dr.) for equipment and materials storage.

The following work and traffic management activities are anticipated for this week: 

Work Activities:

  • NY Waterway may berth multiple ferry vessels at the southern piers of the former Union Dry Dock site. No maintenance work will be performed.  
  • NY Waterway may berth a ferry vessel on the southern side of the northern pier to facilitate work by a contractor on the adjacent piers.  
  • NY Waterway’s contractor will be installing electrical site improvements, including new pedestrian-level lighting on the piers.  
No items found.
Hoboken City Hall Portico Restoration and Foundation Waterproofing Projects

Phase two of the City Hall Portico Restoration Project builds upon the stone patching, roofing tile, and framing replacements, which were completed in 2020 by repointing and restoring the original masonry.

The following work activities are anticipated for the week of June 30, 2025, between the hours of 8 a.m. and 4 p.m.:  

Work Activities  

  • Stone patching and replacement

Traffic and Pedestrian Impacts:  

  • The sidewalk on Washington Street between Newark Street and First Street will temporarily be closed during construction hours of 8 a.m. to 4 p.m. to allow for the delivery of materials to a truck parked on Washington Street.  
  • The Washington Street entrance to Hoboken City Hall will be closed for the duration of the Portico Restoration project.  
  • Hoboken community members must enter and exit City Hall through the Newark Street entrance located between Washington Street and Bloomfield Street.
  • Pedestrians should follow detours during periods when sidewalks in the area are closed for safety reasons.  
  • Signs will be posted, and barricades will be in place.

No items found.
Hoboken Connect

The Hoboken Yard Redevelopment Plan will revitalize southeastern sections of Hoboken, including the Hoboken Terminal and the area around it. The Hoboken Connect project, within the redevelopment Plan area which is being overseen by LCOR, will include a new NJ Transit bus terminal including an indoor market, the rehabilitation of the Ferry Terminal and Warrington Plaza, the rehabilitation of Hudson Place which will turn parts of the road into a pedestrian and retail plaza, as well as  the development of an office building and a residential building that incorporates affordable housing units.  

In 2024, the Consigli Construction Company began construction on the first phase of Hoboken Connect, a 28-story residential building at 111 Observer Hwy, between Washington and Bloomfield Streets. This project will require the temporary relocation of NJ Transit bus stops on both sides of Observer Highway between Washington and Bloomfield Streets to between Bloomfield and Garden Streets. Bike lanes will also temporarily be relocated from the south curbside of Observer Hwy between Bloomfield Street and Washington Street to the north curbside of the same block. The sidewalk and bike lanes along the south curbside of Observer Highway between Bloomfield Street and Washington Street will be closed to pedestrians and these changes are expected to be in place through approximately December of 2026.

This project also required the temporary removal of bicycle parking on Hudson Place between Hudson Street and River Street. New temporary bike parking/racks have been added along Hudson Street. Read more on the temporary changes here: http://local.nixle.com/alert/11466871/  

Residential property at 111 Observer Highway

The following construction activities and traffic management are anticipated to take place from June 30, through Friday, July 4, between the hours of 7:00 a.m. and 5 p.m. by Consigli Construction Company.

Construction Activities

  • Caisson drilling will continue within the boundaries of the construction fence. Some deliveries are anticipated this week. They will be brought in through the construction gates on Observer. Construction flaggers will be used to back trucks into the site.
  • Sitework contractor will be trucking excess soil. This will be scheduled around our concrete pours.
  • Sitework contractor will continue installation of detention tank system on site. Activity will require trucking of soil. Mobile crane will be set up on site within the construction fence to set precast structures.
  • Test pit at 16” water main may take place at the northern lanes of Observer Hwy. Hours for this operation will be 9am-4pm. We will try to schedule this work 1 day next week and coordinate availability of OEP, Veolia, and Suburban Consulting.
  • Note that the site will be closed on Friday, 7/4, and Saturday 7/5 in observance of the July 4th Holiday.  

Traffic Management

  • Construction flaggers will be present for intermittent truck traffic in and out of the site at the construction gates on Observer.

Hoboken Terminal & Hudson Place Area

The following construction activities and traffic management are anticipated to take place from Monday June 30, through Friday, July 4, between the hours of 7:00 a.m. and 3:30 p.m. by Hunter Roberts Construction Group.

Construction Activities

  • Site Work at Old Bus Entrance
    • Grading, site storm line, and electrical / low voltage underground installation
    • Foundation rebar installation for new bus shelters, possible concrete pours for curbs and foundations.
  • YMCA Building Roof Replacement
    • Roofers will continue working on replacing the roof at the YMCA building at Hoboken Train Station.
  • Ferry Terminal Abatement
    • Asbestos abatement work will continue at the second floor of the Ferry Terminal Building.
  • Ferry Terminal Façade
    • Copper façade removal and restoration continues.
  • Site Work at Warrington Plaza
    • Test pits will be dug inside the site fence
    • Pedestrian traffic flow remains unchanged from this week’s set up.  
    • Pile driving starts 7/1. Equipment and material delivery begins 6/30. Pile tractor trailer length is approximately 70’ plus cab. These deliveries will continue daily.
    • Driven pile installation is approximately 2-3 weeks. Drilled piles also start 7/1 and continue into October.
    • Dump trucks will leave the site daily with existing debris removals

Traffic Management

  • Construction flaggers will be present for intermittent truck traffic in and out of the site at the corner of Hudson St and Observer Highway.
  • Construction flaggers will be preset for truck traffic in and out of the site at Warrington Plaza.

No items found.
15th Street Roadway Improvements

The 15th Street Roadway Improvement Project will reconstruct 15th Street from Madison Street to Adams Street and Willow Avenue to Park Avenue and will include critical Vision Zero and resiliency upgrades to transform the road to a more protected, accessible, and resilient pathway for all users. The Improvement Project will also construct a segment of the Green Circuit.

This is part of an overall larger project which will raise portions of the northern end of Hoboken to reduce nuisance flooding. Work includes new curbs, sidewalks, a raised bike lane, decorative lighting, street trees, and associated striping. The milling, overlay, and re-striping of 15th Street between Willow and Park is also included in this project.  

Phase One, which started June 16, is expected to be completed by mid-November and will reconstruct 15th Street from Madison Street to Adams Street. Phase Two, which includes resurfacing between Willow Avenue and Park Avenue, is expected to begin later this year.  

The following construction activities and traffic management are anticipated to take place from Monday, June 30, 2025 through Friday, July 4, 2025, between the hours of 7 a.m. and 5 p.m. by Reivax Contracting.

Construction Activities

  • Installation of a concrete knee wall will take place in the southern sidewalk area of 15th Street between Madison Street and Jefferson Street.
  • Demolition of the sidewalk area for the construction of a knee wall will take place on 15th Street between Jefferson Street and Adams Street.
  • There will be no work on Thursday (7/3) or Friday (7/4) for the 4th of July holiday.

Traffic Management

  • One-lane of traffic will remain open at all times to allow traffic to flow.  
  • Temporary No-Parking signs will be posted on both sides of the roadway at these locations to allow a lane of traffic to flow.
  • Sidewalks will be closed at some locations during knee wall construction.  Pedestrian detours will be posted.
  • Hoboken Police will be onsite to assist with lane shifts and pedestrian detours.

Picture

No items found.